DD2076 Royal Albert Dock – Second Deed of Variation

Key information

Decision type: Director

Reference code: DD2076

Date signed:

Decision by: David Lunts, Chief Executive Officer, Old Oak and Park Royal Development Corporation

Executive summary

GLA Land & Property Limited (GLAP) entered a Development Agreement with ABP London Investment Ltd on 23 May 2013 for the regeneration of Royal Albert Dock.

ABP submitted their Business Plan for Phase 1 of the scheme in October 2016. The plan sets out ABP’s proposed approach to the delivery of phase 1. These proposals require a minor variation to the Development Agreement to ensure the continued protection of GLA’s commercial interests.

Decision

The Executive Director of Housing & Land is asked to APPROVE the proposed changes to the Development Agreement and enter into a Deed of Variation to document the changes.

Part 1: Non-confidential facts and advice

1.1 GLA Land and Property Ltd (GLAP) entered a Development Agreement (DA) with ABP London Investment Ltd (ABP) on 23 May 2013 for the regeneration of Royal Albert Dock. When complete, the site will be a new commercial business hub in the east of London, supported by substantial retail, leisure and community facilities and transport infrastructure upgrades. The development is designed to attract investment from Chinese and Far Eastern companies seeking to establish a UK presence as well as London based companies seeking to relocate.
1.2 Hybrid planning permission was granted for the scheme on 22nd December 2015 and provides consent for:
- 4.7m sqft GEA of development comprising;
- 3.29m sqft of office space
- 935,000 sqft of residential development (up to 845 homes)
- 165,824 sqft of retail/leisure floor space
1.3 The project has moved into its next phase and GLAP is working closely with ABP to enable a start on site in early 2017. Early enabling works have already been completed to prepare the site for construction.
1.4 Before it can draw down the head lease for phase 1, ABP must satisfy a range of Conditions Precedent. Good progress has been made in recent months to close out these conditions. In particular:
- GLAP has approved ABP’s Annual Business Plan
- GLAP has approved the identity of the Building Contractor (CITIC and Multiplex)
- ABP has entered the Building Contract for phase 1
- An escrow account has been opened, ready for ABP to deposit GLA’s development security
- The head lease for phase 1 has been drafted and is close to agreement

2. Phase 1 Business Plan
2.1 ABP submitted its Business Plan for Phase 1 to GLAP in late October 2016. Under the terms of the DA, ABP must secure GLAP’s approval to this plan and this too is a Condition Precedent to the grant of the Phase 1 head lease.
2.2 GLAP has closely scrutinised the plan with input from its legal and property advisors. The plan includes ABP’s proposed corporate and development structure. As a result of this proposed structure, a minor amendment to the DA is required to protect GLAP’s commercial interests. Further details are in part 2 of this paper.

3.1 It is not anticipated that the recommended amendments to the Development Agreement will have a negative impact on any groups identified under the Equality Act 2010.

This paper is seeking approval for changes to the DA.

5.1 See Part 2

Activity

Timeline

Complete deed of variation

23 December 2016

Relevant entities to sign a deed of adherence

23 December 2016

Start on site

Spring 2017

Signed decision document

DD2076 Second RAD variation (signed) PDF

Need a document on this page in an accessible format?

If you use assistive technology (such as a screen reader) and need a version of a PDF or other document on this page in a more accessible format, please get in touch via our online form and tell us which format you need.

It will also help us if you tell us which assistive technology you use. We’ll consider your request and get back to you in 5 working days.