Skip to main content
Mayor of London logo London Assembly logo
Home

MD1570 Croxley Rail Link

Key information

Decision type: Mayor

Reference code: MD1570

Date signed:

Decision by: Boris Johnson, Former Mayor of London (May 2008 - May 2016)

Executive summary

In accordance with Mayoral Decision MD1478, Transport for London (TfL) and Hertfordshire County Council (HCC) have agreed the detailed arrangements for the transfer to TfL of the Croxley Rail Link scheme, and an HCC led local consortium funding contribution.
HCC’s portion of the local consortium funding contribution includes two parcels of land to which HCC have attributed a total value of £2.73m. The first parcel, comprising the disused rail corridor (to which a value of £1.8m has been attributed) will be transferred by Network Rail to LUL for a nominal consideration. The second parcel will be used by LUL as a work site during construction. Roughly 25% of it will be transferred to LUL, although title to the remainder will be retained by HCC, and used as a station car park, which HCC will operate for its own account. The cash element of the local consortium funding will be reduced by £2.73m to £125.35m.

Decision

The Mayor:

1. Directs TfL to proceed in accordance with the directions given under MD1478 but on the basis that the HCC led local consortium nominal funding contribution of £128.08m includes land contributions by HCC which while valued by HCC at £2.73m are of no commercial value to TfL, and that the cash contribution will therefore be £125.35m

2. Directs TfL to provide up to a further £2.73m of funding in addition to the £46.5m directed under MD 1478 towards the costs for delivering Croxley Rail Link

Part 1: Non-confidential facts and advice

1. Introduction and background

1.1 The Croxley Rail Link (CRL) project involves the diversion and extension of the existing Metropolitan line from just north of Croxley to a new terminus at Watford Junction via the existing Watford High Street with two new stations. The existing Metropolitan line terminus at Watford station will close.

1.2 On 26 March 2015 the Mayor directed TfL, under MD1478:

  • to take over responsibility for delivering the entire project including civil engineering works, systems and the procurement of additional rolling stock.
  • to provide £46.5m of funding towards the costs for delivering Croxley Rail Link based on a total cost of the project of £284.4m on the basis that the Government increased TfL’s overall borrowing requirement by £30m and that £16m would be funded from the TfL capital budget (the remaining costs of £238m were to be funded from HCC and the DfT).
  • to be responsible for any cost overruns above the current project estimate of £284.4m

1.3 HCC is leading a consortium of funding partners (including the Hertfordshire Local Enterprise Partnership and Watford Borough Council) who were to contribute £128.08 million to the total costs of the project. The detailed arrangements for payment of this funding were to be agreed separately between TfL and HCC.

2. Objectives and expected outcomes

2.1 The key objectives for the CRL are to provide a catalyst for regeneration and growth in the Watford area and improve connectivity between SW Hertfordshire and NW London.

3. Equality comments

3.1 The new stations will both be fully step-free and include all standard accessibility features. No adverse effects are foreseen on any persons with protected characteristics under the Equality Act 2010.

4. Risks

Reputational

4.1 The proposed change of delivery strategy would increase TfL’s visibility in the eyes of the public and media, making TfL more exposed in the event of future cost increases or programme delays.
Cost

4.2 The proposed funding strategy would mean TfL potentially needing to contribute more than £16m should the overall cost be higher than the funding package of £284.4m. The current P50 estimate for the project is £299m. Outturn at this level would require additional TfL funding of £15m. The cost escalation has arisen primarily due to the level of sunk cost incurred by HCC being higher than had been anticipated at the time of the 26 March 2015 MD.

5. Financial comments

5.1 MD1478 noted, at paragraph 5.4, that the following breakdown of funding had been agreed for the scheme:

Funding Partner £m
Department of Transport 109.82
Transport for London (including fare box borrowing) 46.50
Hertfordshire LEP 87.85
HCC & Watford Borough Council 40.23
TOTAL FUNDING 284.40

5.2 The local consortium funding contribution breakdown is as follows:

Funding Partner £m
HCC 30.635
Hertfordshire Local Enterprise Partnership 87.850
Watford Borough Council 9.595
Total consortium funding contribution 128.08

5.3 HCC’s funding contribution breakdown, which has been approved by its Cabinet, is as follows:

HCC Contribution £m
Capital 25.000
s.106 2.905
Land contributions 2.730
Total HCC funding contribution 30.635

5.4 HCC’s portion of the £128.08m local consortium funding contribution includes two parcels of land to which HCC have attributed a total value of £2.73m. The first parcel, comprising land between Ascot Road and Wiggenhall Road (to which a value of £1.8m has been attributed) will be transferred by Network Rail to LUL for a nominal consideration of £1. This land is assumed to have limited commercial value. The second parcel of land at Ascot Road will be used by LUL as a work site during construction. Roughly 25% of it will be transferred to LUL although title to the remainder will be retained by HCC and used as a station car park which HCC will operate for its own account. Again, the commercial value is likely to be limited.

The cash element of the local consortium funding will be reduced by £2.73m to £125.35m.

5.5 Accepting HCC’s land contribution on the basis of its £2.73m valuation, as set out above, will reduce by the same amount the cash element of the £128.08m local consortium funding contribution that would be paid to TfL.

5.6 The overall funding envelope remains £284.4m and if the project is delivered, in full, for a total cost below the approved budget cost of £284.4m, TfL will retain the full amount of the resulting cost savings. TfL will still meet any eligible project costs incurred over £284.4m.

5.7 There remain no financial implications for the GLA.

6. Legal comments

6.1 The proposed further direction raises no legal issues not considered in MD 1478.

8.1 TfL’s latest programme is in the table below:

Activity Timeline
Procurement of contract [notice to proceed with construction phase issued] Feb. 2016
Delivery Start Date Apr. 2016
Delivery End Date [start of operational service] Dec. 2020
Project closure: Sep. 2021

Direction to Transport for London (supplemental to Direction of 26 March 2015)

Supporting documents

MD1570 Croxley Rail Link (signed form and Direction)

Need a document on this page in an accessible format?

If you use assistive technology (such as a screen reader) and need a version of a PDF or other document on this page in a more accessible format, please get in touch via our online form and tell us which format you need.

It will also help us if you tell us which assistive technology you use. We’ll consider your request and get back to you in 5 working days.